Hard Work Always Pays Off

We headed up to our Cabin with plans of getting a lot of work done. We were both feeling strong and determined. We brought Stitch for moral support and foot rubs.

I don’t do foot rubs…

After crossing The Mighty Mac, we arrived to set up camp and prepare for work. We hoped to get the garage dried in, and cabin sided.

Mighty Mac

First we tackled details with the garage. Using scaffolding and ladders, we made rafter tails, added blocks between the rafters, and added fascia board.

Off to a good start
Side view
Putting up OSB for F-channel for Soffits

To reach all the heights, we rented a Nifty Fifty for the week: an articulating lift that is operator driven from the basket.

Green Giant

This helped us reach the tall areas of the garage to build soffits on all sides. J manned the lift while I operated the chop saw.

Reaching new heights
Chop chop

In order to put up fascia, the ends needed to be cut at the back of the garage or extended at the front of the garage. This will give a 16 inch soffit at the front and a slightly narrower one at the back. We had purchased 16 foot rafters rather than 18 foot for the cost ($17 per board), so we had to make this small adjustment. The back of the garage will face the back deck, so it will be less obtrusive with the narrower soffit.

Securing the fascia board

After a hearty breakfast, we were ready to tackle the vertical boards on the sides of the garage so we could continue to dry in the building.

Kodiak cakes for the win
Installing the verticals

With only a crew of 2, we found a rhythm in J doing the climbing, measuring, calling out measurements, me doing the chopping and the handing up of boards.

Waiting on the next cut
Force Field OSB installed
We worked from dawn to dusk!

The next day was OSB on the roof day, or Leg and Worry Day. I’ll leave it to the reader on who did what…

The first row was the easiest
Roofing is no joke

In addition to worrying, I would use the circular saw to cut the OSB to length and help lift it up, while climbing on the scaffolding to pass it up. J muscled each sheet, secured in place and added foot holds for the next row.

All dried in!!

Next, we needed to add the synthetic roof paper. This involved more roof time, wrangling long sheets of roof paper and repositioning the stepping boards.

The first row is the easiest (again)
The supervisor came out to check on the crew
Well earned break!

The next order of business was tackling the siding. Front of cabin first…

Reaching the peak

Again, as with the framing and roofing, teamwork prevailed. I cut the cement board siding and carried them up to the second floor and handed them out the windows to J as he installed, then measured for the next piece. These were my Leg Days…

Second side of house done

Before tackling the back, and last side of the house, we decided to keep NF (Nifty Fifty, not the rapper) on the one side of the house and tackle the adjacent side of the garage. So, in order to do that, we needed to install windows and door.

Eyes to the soul
Knock knock
Garage side done

On our last day, we pushed hard to finish the back side of the house. It was a very hot and humid day. There were a few extras we had to do earlier in the week in preparation for this side. We fortified the wall and garage roof where they meet to make sure no water ever pools in this area.

Extra protection from water and snow
The final push
Still chopping
So close, but so far…

The next morning, we returned NF, boarded up the garage and put a lock on the door. We worked for 10 days straight, and got a lot done. We need to celebrate our wins, and congratulate one another on a job well done. We went home full of ibuprofen and smelling like tiger balm. Hooha! J & M

How we felt after 10 days of work..
Hard work is always worth it

Father’s Day Weekend Fun

This year for Father’s Day, the boys generously offered their time and muscle to working on the cabin. First job: construct and put up garage door header. This consisted of 2 20 foot 12-inch LVLs for a code-approved header.

There’s the beef

The next order of business required building a walkway to allow for safe working conditions when constructing the rafters. This walkway will be left up and serve as storage area in the garage.

Safe and practical

Next, the ridge poles were built. This helps hold the ridge beam in place until all the rafters are built and set in place.

So far so good

With the ridge beam in place, the rafters could be installed. This process included cutting and notching the 16 foot boards, then installing them on one side of the beam, then the other, 1 foot on center to bear the weight of the UP snow.

Raise the roof!

Father’s Day was beautiful, so we decided to take a trip into Munising for a ‘break’.

Ruh roh

Apparently, getting down from the scaffolding, an ankle was sprained and 5th metatarsal fractured (again). Fortunately it is a small break, unfortunately it delays drivers ed classes for the summer.

Spirits staying high

With one man down, the job of completing the roof was on a crew of two. The goal was to get all the rafters set before heading home.

Mission accomplished!

The weekend was successful, with some quality time spent together creating the family cabin. It was definitely a Father’s Day to remember. Next trip, we will focus on closing in the garage, and hopefully finishing up the siding. Until then, hooha! J + M

Good things come from hard work